Why The Sandwich Panel Delivery Time Is 35–45 Days

Dec 22, 2025 Leave a message

For most projects, the delivery time for sandwich panels is 35–45 days after receiving the down payment and confirming the final drawings.

 

This is because sandwich panels are customized products, and the production process requires sufficient time to ensure quality and accuracy.

Raw material of sandwich panel

Day
1-7

 

Raw Material Confirmation

Our engineers carefully review the approved drawings and BOQ to confirm the exact quantities of sandwich panels and related accessories.
This step ensures sufficient raw material preparation and avoids any shortage of panels or accessories in specific colors during later production stages.

 

Profile mould

Day
11-30

 

Raw Material Procurement & Shop Drawing Design / Approval

Sandwich panels are produced according to project-specific requirements, including:
• Panel thickness
• Steel sheet thickness
• Profile type
• Color selection

We use well-known Chinese pre-painted steel coil brands (Guanzhou) as raw materials.
After order confirmation, steel coils must be scheduled, prepared, and cut exclusively for each project, which requires lead time and cannot be supplied directly from stock.

At the same time, shop drawings are designed, reviewed, and confirmed, ensuring all production details are fully aligned before manufacturing starts.

 

product line of sandwich panel

Day
31-40

 

Production Preparation, Manufacturing & Quality Inspection

Since different panel types and profiles require different molds, mold changes and production adjustments are necessary before manufacturing.

During production:

First-piece inspection is carried out

In-process inspections are conducted to ensure consistent quality

 

⚠️ Please note:

If an order includes too many panel types or specifications, it will directly affect production duration due to frequent mold changes and adjustments.

 

package of sandwich panel

Day
41-
42

 

Packing

Packing requires 2–3 days, especially for overseas projects.

Customized packing solutions are applied to:

Protect panels during long-distance container transportation

Improve unloading efficiency

 

✅ Why This Timeline Matters

 

This structured timeline ensures stable quality, accurate quantities, and smooth on-site unloading.

The 35–45 day lead time is a carefully managed process - not a delay - designed to reduce risks and deliver reliable project performance.

 